City of Boston
 
 
Public Works Department
Contact Us
 
City Departments
Resurfacing By Neighborhood And Street

You can find a working list of streets below that the City of Boston plans on resurfacing or reconstructing during the 2018 construction season. This list is subject to change and may be altered to accommodate necessary underground infrastructure improvements or other unforeseen circumstances.

If you live on a street that is proposed for resurfacing or reconstruction and are thinking about installing a new service or upgrading a current service for your building, it is critical that you refer to our utilities fact sheet

Any delay may result in the street being paved and your ability to receive a permit for a service connection denied.

We created a page to explain the resurfacing process in more detail. If you have any questions, please contact the Construction Management division of Public Works at 617-635-4950.


Search By:     Or By:
NeighborhoodStreetFrom StreetTo StreetWork TypeEstimated StartDurationStatusCompleted
Allston/BrightonADAIR STFANEUIL STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonBEACON STAYR RDCHESTNUT HILL AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonBENNETT STMARKET STPARSONS STFull ReconstructionAPRIL- AUGUST5 MONTHSACTIVE 
Allston/BrightonBIGELOW STJUSTIN RDBROOKS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED/ON HOLD…CURRENTYCOORDINATING UTILITY WORK TO BE DONE BEFORE WE PAVE 
Allston/BrightonBLAINE STBRAINTREE STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonBRAINARD RDHARVARD AV GRIGGS STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonBRIGHTON AV@CHESTER ST@CHESTER STSidewalk ReconstructionMAY- JULY3 MONTHSACTIVE 
Allston/BrightonCHARLESVIEW STBIGELOW STNEWTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonCHESTNUT HILL AVBEACON STCOMMONWEALTH AVFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Allston/BrightonCHESTNUT HILL AV@ WINSHIP STNASidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Allston/BrightonCOMMONWEALTH AV EBESSEX STNAPLES STMassDOT ReconstructionNOVEMBER 2017 -NOVEMBER 20181 YEARACTIVE/MASSDOT RECON /NEWPORT CONTRACTOR 
Allston/BrightonCOMMONWEALTH AV WBUNIVERSITY RDALCORN STMassDOT ReconstructionNOVEMBER 2017 - NOVEMBER 20181 YEARACTIVE/MASSDOT RECON /NEWPORT CONTRACTOR 
Allston/BrightonCUMMINGS RDCOREY RDSERVICE RDCapital ResurfacingMAY2 WEEKSCOMPLETED 5/10/2018
Allston/BrightonCUSHMAN RDGLENCOE STDUSTIN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonDICKINSON RDWASHINGTON STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonENGLEWOOD AVSUTHERLAND RDCHESNUT HILL AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonFISKE TERBRAINERD RDBROOKLINE TOWN LINECapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonFORDHAM RDBRIGHTON AV EB LANE (EVEN)SERVICE RD (OFF COMM AV WB)Capital ResurfacingMAY2 WEEKSCOMPLETED5/10/18
Allston/BrightonGREYMERE RDWASHINGTON ST BRDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonHASKELL STHOOKER STCOOLIDGE RD BRAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonHIGH ROCK WAYIMRIE RDGORDON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonHOBSON STFANEUIL STHOBART STAsphalt ResurfacingAPRIL2 WEEKSCOMPLETED5/1/18
Allston/BrightonHUNNEWELL AVMATCHETT STBURTON STAsphalt ResurfacingAPRIL2 WEEKSCOMPLETED4/30/18
Allston/BrightonJORDAN RDCOREY RDBROOKLINE TOWN LINEAsphalt ResurfacingAPRIL2 WEEKSCOMPLETED/ ARP CARRY OVER5/3/18
Allston/BrightonLANE PARKFOSTER ST BRLANE PARKCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonLAROSE PLMONASTERY RDDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonMALBERT RDWASHINTON ST BRDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonMT VERNON ST BRACADEMY HILL RD FOSTER ST BRAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonNORTH CRESCENT CIRCUITBRECK AVDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonPRESENTATION RDWASHINGTON ST BRHUNNEWELL AVCapital ResurfacingMAY2 WEEKSCOMPLETED5/10/18
Allston/BrightonQUINT AVBRIGHTON AV EB LANE (EVEN)GLENVILLE AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonRANSOM RDCLAYMOSS RDCOLBORNE RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonROYCE RDSERVICE RD (OFF COMM AV EB)BRAINERD RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonRUSHMORE STACADEMY HILL RDMICHAEL RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonSNOW STWASHINGTON STUNION STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonST LUKES RDBRIGHTON AV EB LANE (EVEN)SERVICE RD (OFF COMM AV WB)Asphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Allston/BrightonSUMMIT AVALLSTON STSERVICE RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSCOMPLETED5/3/18
Allston/BrightonSURREY STMARKET STFOSTERAsphalt ResurfacingAPRIL2 WEEKSCOMPLETED 5/2/18
Allston/BrightonWILLISTON RDCOREY RDBROOKLINE TOWN LINEAsphalt ResurfacingAPRIL-MAY2 WEEKSCOMPLETED5/3/18
Allston/BrightonWILSHIRE RDCHESTNUT HILL AVDEAD ENDAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
Allston/BrightonWM JACKSON AVCHESTNUT HILL AVDEAD ENDAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
Allston/BrightonWOODMONT STBROOKS ST BRDEAD ENDAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
Back BayARLINGTON STISABELA STMELROSE STFull ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Back BayBOYLSTON STEXETER STFAIRFIELD STSidewalk ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Back BayCOMMONWEALTH AV EBHEREFORD STCHARLESGATE EASTMassDOT ResurfacingLATE JUNE/EARLY JULY2 WEEKSCOMPLETED7/6/18
Back BayCOMMONWEALTH AV WBHEREFORD STCHARLESGATE EASTMassDOT ResurfacingLATE JUNE/EARLY JULY2 WEEKSCOMPLETED7/6/18
Back BayMASSACHSUETTS AVPUBLIC ALLEY 430MARLBOROUGH STMassDOT ResurfacingJULY2 WEEKSNOT STARTED 
Back BayPUBLIC ALLEY 424CLARENDON STDARTMOUTH STAsphalt ResurfacingTBD1 WEEKNOT STARTED 
Back BayPUBLIC ALLEY 434PUBLIC ALLEY 435PUBLIC ALLEY 433Asphalt ResurfacingTBD2 WEEKSNOT STARTED  
Back BayPUBLIC ALLEY 437ARLINGTON ST BERKELEY STCapital ResurfacingTBD2 WEEKSNOT STARTED  
Back BayPUBLIC ALLEY 439CLARENDON STDARTMOUTH STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
Beacon HillBEACON STPARK STARLINGTON ST BPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Beacon HillBEACON STTREMONT STPARK STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Beacon HillBRANCH STSPRUCE STCLARLES STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Beacon HillJOY STBEACON STSMITH CTFull Reconstruction2017TBDNOT STARTED/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Beacon HillWALNUT STBEACON STMT VERNON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Boston ProperBATTERYMARCH STWATER STHIGH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Boston ProperCOURT STAT COURT SQUARE@ COURT SQUARESidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED 
Boston ProperDEVONSHIRE ST@ OLD STATE HOUSE@ OLD STATE HOUSESidewalk ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED  
Boston ProperFRIEND STMARKET STCAUSEWAY ST EB ODDFull ReconstructionTBDTBDNOT STARTED  
Boston ProperHANOVER STCONGRESS STBLACKSTONE STFull ReconstructionJUNE - NOVEMBER6 MONTHSNOT STARTED/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperMARGINAL RDSHAWMUT AVARLINGTON STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
Boston ProperMARSH LNUNION STCREEK SQFull ReconstructionNOVEMBER 20181 YEARACTIVE/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperMARSHALL STHANOVER STUNION STFull ReconstructionNOVEMBER 20181 YEARACTIVE/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperNORTH STUNION STSURFACE ARTERY RDFull ReconstructionTBDTBD NOT STARTED/CONNECT HISTORIC BOSTON 
Boston ProperNORTH STCONGRESS STUNION STFull ReconstructionNOVEMBER 20181 YEARACTIVE/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperOLIVER STMILK STHIGH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Boston ProperPUBLIC ALLEY 102MARSHALL STCREEK SQFull ReconstructionTBDTBDNOT STARTED/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperSALT LNUNION STSCOTT ALLEYFull ReconstructionNOVEMBER 20181 YEARACTIVE/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperSCOTT ALLEYCREEK SQDEAD ENDFull ReconstructionNOVEMBER 20181 YEARACTIVE/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperSTATE ST@ KILBY STAT KILBY STSidewalk ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED 
Boston ProperUNION STNORTH STHANOVER STFull ReconstructionNOVEMBER 20181 YEARACTIVE/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
Boston ProperWINTHROP SQUAREAT OTIS ST @DEVONSHIRE STREETSAT OTIS @ DEVONSHIRE STREETSSidewalk ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED  
CharlestownBUNKER HILL CTBUNKER HILL STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownCEDAR STHIGH STBARTLETT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownCHARBONNIER STMAIN STMAIN STAsphalt ResurfacingTBD2 WEEKSNOT STARTED 
CharlestownCONCORD STMONUMENT SQBUNKER HILL STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
CharlestownCONSTITUTION RDCHAMBER STCHELSEA STFull ReconstructionNOVEMBER 2018I YEARACTIVE/RECONSTRUCTION/CONNECT HISTORIC BOSTON 
CharlestownCROSS STHIGH STTRENTON STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
CharlestownDECATUR STVINE ST MEDFORD STAsphalt ResurfacingTBD2 WEEKSNOT STARTED 
CharlestownFIRST AVFIFTH STTHIRTEENTH STAsphalt ResurfacingTBDTBDNOT STARTED 
CharlestownHENLEY STHARVARD SQWARREN STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
CharlestownHILL STDEAD ENDCOOK STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
CharlestownHUNTER STBUNKER HILL STVINE STAsphalt ResurfacingJULYTBDNOT STARTED 
CharlestownLYNDE STUNION STNEW RUTHERFORD AVAsphalt ResurfacingTBD2 WEEKSNOT STARTED 
CharlestownMONUMENT SQCHESTNUT STCHESTNUT STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
CharlestownMONUMENT STMONUMENT SQBUNKER HILL STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownNEAREN ROWTREMONT STFERRIN STAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
CharlestownNEW RUTHERFORD AVRUTHERFORD AVMISHAWUM STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownPLEASANT STDEVENS STMONUMENT SQAsphalt ResurfacingTBD2 WEEKSNOT STARTED  
CharlestownSEVENTH STTHIRD AVFIRST AVAsphalt ResurfacingTBDTBDNOT STARTED 
CharlestownSUMMER STELM STSCHOOL STAsphalt ResurfacingJULYTBDNOT STARTED 
CharlestownTREMONT STPROSPECT STLOWNEY WAYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownTUFTS STBUNKER HILL STMEDFORD STAsphalt ResurfacingJULYTBDNOT STARTED 
CharlestownWALFORD WAYTUFTS STPOLK STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownWALFORD WAYDECATUR STSTARR KING CTAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownWALKER STMAIN STWALL STAsphalt ResurfacingJULYTBDNOT STARTED 
CharlestownWARREN STHENLY STMONUMENT AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
CharlestownWOOD STMAIN STHIGH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
ChinatownBEACH STATLANTIC AVSURFACE ROADFull ReconstructionTBD6 MONTHSNOT STARTED 
DorchesterANSEL ST(EVEN)ASHTON STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterARBORCREST TERGLADESIDE AVRIDGEVIEW AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterASPINWALL STWASHINGTON STTALBOT AVCapital ResurfacingMAY2 WEEKSCOMPLETED5/21/18
DorchesterBALINA PLNORFOLK STDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBARRINGTON RDBEAUMONT STELMER RDCapital ResurfacingLATE JUNE INTO JULY2 WEEKSCOMPLETED6/29/18
DorchesterBEACH STFREEPORT STPARK STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBEALE STDORCHESTER AVDEAD ENDCapital ResurfacingMAY2 WEEKSCOMPLETED5/23/18
DorchesterBLANCHE STEVERDEAN STVICTORY RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBRANCHFIELD STMEDWAY STBUTLER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED/ NEW GAS MAIN THIS SUMMER/ RESURFACE IN FALL 
DorchesterBUSHNELL STASHMONT STWEYANOKE STCapital ResurfacingJUNE2 WEEKSCOMPLETED6/26/18
DorchesterCARRUTH STASHMONT STGALLIVAN BLVDCapital ResurfacingAPRIL- MAY2 WEEKSCOMPLETED5/3/18
DorchesterCHURCH STWINTER STFRUEAN PLAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterCLOVER STMINOT STGALLIVAN BLVDAsphalt ResurfacingJUNE INTO JULY2 WEEKSCOMPLETED6/29/18
DorchesterCONLEY STTENEAN STMORRISSEY BLVDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterDAVITT STSAVIN HILL AVEDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterDORCHESTER AVAT LINDEN STAT LINDEN STSignal Installation WorkTO BE DETERMINED2 MONTHSNOT STARTED 
DorchesterDUNBAR STWASHINGTON STWENTWORTH TERAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterEAST COTTAGE ST HUMPHREYS STNORFOLK AVSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
DorchesterEAST STCHURCH STADAMS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterEDSON STNORFOLK STMILTON AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterELTON STDORCHESTER AVEAUCKLAND STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterELY RDFREDERIKA STKENMARE RDAsphalt ResurfacingTBDTBDNOT STARTED 
DorchesterEUCLID STWASHINGTON STWITHINGTON STSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED/ON HOLD…CURRENTYCOORDINATING UTILITY WORK TO BE DONE BEFORE WE PAVE 
DorchesterFAIRMOUNT STMILTON AVMORTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterFRANCONIA STADAMS STCHARLEMONT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterFREEPORT WAYFREEPORT STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
DorchesterGENE STHUMPHREYS STBELDEN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterGENEVA AVAT CHARLES AND WALDECK STREETSAT CHARLES AND WALDECK STREETSSignal Installation WorkTO BE DETERMINED2 MONTHSNOT STARTED 
DorchesterHOLDEN STCOLUMBIA RDBELDEN STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterHOWARD AVEDUDLEY STHARTFORD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
DorchesterHOWE STHANCOCK STHOWE TERAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
DorchesterHUMES RDASHMONT STNAHANT AVAsphalt ResurfacingMAY2 WEEKSCOMPLETED 5/15/18
DorchesterHUMPHREYS PLHUMPHREYS STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterIRMA STCALLENDER STWOODROW AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterJOANNE TERADAMS STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterKANE STBELLEVUE STSTANLEY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
DorchesterKINGSDALE STSTANDISH STBERNARD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterLABAN PRATT RDBOUTWELL STWESTGLOW STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterMAYBROOK STGLENWAY STGREENWOOD STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterMCKONE STNEPONSET AVMORRISSEY BLVDCapital ResurfacingLATE JUNE INTO JULY2 WEEKSCOMPLETED6/29/18
DorchesterMENTON STGROVELAND STSTANDARD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterMILLET STPARK STTALBOT AVEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
DorchesterMILWOOD STGALLIVAN BLVDMILTON AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterMINOT STADAMS STCARRUTH STCapital ResurfacingLATE JUNE INTO JULY2 WEEKSCOMPLETED6/29/18
DorchesterMT EVERETT STQUINCY STHAMILTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
DorchesterMT VERNON STMORRISSEY BLVDENDAsphalt ResurfacingMAY2 WEEKSCOMPLETED 5/14/18
DorchesterNEW ENGLAND AVTALBOT AVWOODROW AVFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED  
DorchesterNONQUITDUDLEY STDEAD ENDCapital ResurfacingMAY2 WEEKSCOMPLETED5/30/18
DorchesterNORTH AVEDUDLEY STBROOK AVECapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterOAKTON AVADAMS STPIERCE AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterODONNELL TERCENTRE STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterOGDEN STFAIRMOUNT STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterOLD MORTON STPLEASANT HILL AVSANFORD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterOLD RDMICHIGAN AVCOLUMBIA RDSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
DorchesterPARK STADAMS STDORCHESTER AVCapital ResurfacingMAY2 WEEKSCOMPLETED5/8/18
DorchesterPARK STADAMS STFREEPORT STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED/ACTIVE NEW GAS MAIN WORK/RESURFACING IN FALL 
DorchesterPASADENA RDCOLUMBIA RDBLUE HILL AVECapital ResurfacingJUNE2 WEEKSCOMPLETED6/11/18
DorchesterQUINCEFIELD STHUMPHREYS STWENDOVER STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
DorchesterQUINCY STBLUE HILL AV COLUMBIA RDFull ReconstructionMAY- SEPTEMBER5 MONTHSACTIVE 
DorchesterRADFORD LNCARRUTH STBUSHNELL STCapital ResurfacingLATE JUNE INTO JULY2 WEEKSCOMPLETED6/26/18
DorchesterRICHFIELD STHAMILTON STOLNEY STAsphalt ResurfacingTBDTBDNOT STARTED 
DorchesterRIPLEY RDHARVARD STCARMEN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterROSEDALE STWASHINGTON STWHITFIELD STCapital ResurfacingMAY2 WEEKSCOMPLETED5/17/18
DorchesterROWENA STCARRUTH STBUSHNELLSTCapital ResurfacingJUNE2 WEEKSCOMPLETED6/26/18
DorchesterRUNDEL PARKASHMONT STELMER RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterSAMOSET STROSELAND STWELLES AVCapital ResurfacingMAY-JUNE2 WEEKSNOT STARTED 
DorchesterSANFORD STMORTON STCEDAR STFull ReconstructionMAY-AUGUST4 MONTHSACTIVE 
DorchesterSANTUIT STROSELAND ST WELLES AVAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/15/18
DorchesterSAVIN HILL AVPLEASANT STDORCHESTER AVCapital ResurfacingMAY2 WEEKSCOMPLETED5/8/2018
DorchesterSAVIN HILL AVDORCHESTER AVHUBBARDSTON RDCapital Resurfacing20182 WEEKSNOT STARTED/ ACTIVE UTILITY WORK MAY DELAY PAVING UNTIL 2019 
DorchesterSHENANDOAH STCARRUTH STWESSEX STCapital ResurfacingLATE JUNE 2 WEEKSCOMPLETED6/26/18
DorchesterSOUTHWICK STNEPONSET AVFREEPORT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterTUPELO STSAVIN STQUINCY PLAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterVAN WINKLE STBUSHNELL STCARRUTH STCapital ResurfacingLATE JUNE INTO JULY2 WEEKSCOMPLETED6/26/18
DorchesterVICTORY RDEVERDEAN STVICTORY RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWINSTON RDWILLOWWOOD STFRONTENAC STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWOLCOTT STCOLUMBIA RDERIE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWOLLASTON TERWOODROW AVJONES AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWYOLA STCOLUMBIA RDSUSI YARDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterYORK STGLENWAY STGREENWOOD STCapital ResurfacingMAY2 WEEKSCOMPLETED5/18/18
East BostonBAYSWATER STSARATOGA STST ANDREW RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonBREMEN STSUMNER STMAVERICK STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonCHELSEA STMAVERICK STGEORGE R VISCONTI RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonCOWPER STMOORE STBYRON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonCOWPER STBYRON STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonCURTIS STCHELSEA STCURTIS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonFAYWOOD STCRESTWAY RDORIENT AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonFORD STSARATOGA STBREED STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonFRANKFORT STNEPTUNE RDDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonGEORGE R VISCONTI RDCHELSEA STPARIS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonHAVRE STGEORGE R VISCONTI RDMARION STAsphalt ResurfacingTBDTBDNOT STARTED 
East BostonHORACE STHARMONY STBYRON STCapital ResurfacingTBDTBDNOT STARTED 
East BostonJEFFRIES STMAVERICK STSUMNER STAsphalt ResurfacingTBDTBDNOT STARTED 
East BostonMERIDIAN STLONDON STLONDON STSignal Installation WorkTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonPARIS STSUMNER STMERIDIAN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonPRESCOTT STEAST EAGLE STBREMEN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonPUTNAM STLEXINGTON STCHELSEA STAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/12/18
East BostonSARATOGA STTRIDENT STBURGER KING DRIVEWAYSidewalk ReconstructionTO BE DETERMINED2 WEEKSSIDEWALK RECON 
East BostonTRIDENT STSARATOGA STBENNINGTON STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED RECON/ADVERTISE IN FALL/ LIKELY START IN 2019 
East BostonWHITBY STFORD STDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonWORDSWORTH STCHARLES ERNEST ANDREW FbCOLERIDGE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayAVENUE LOUIS PASTEUR AVFENWAY LONGWOOD AVAsphalt ResurfacingJUNE2 WEEKSCOMPLETED6/16/18
FenwayBINNEY STFRANCIS STCHILDRENS RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayBROOKLINE AVFENWAY BROOKLINE TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED/ COORDINATING UTILITY WORK FIRST/ LIKELY HOLDING OFF PAVING UNTIL THE FALL OR 2019 
FenwayBURBANK STEDGERLY RDHEMENWAY STCapital ResurfacingTO BE DETERMINEDTBDNOT STARTED/ACTIVE BUILDING WORK WILL HOLD OFF PAVING UNTIL THE FALL OR 2019 
FenwayFRANCIS STBROOKLINE AVRIVERWAYAsphalt ResurfacingJUNE2 WEEKSCOMPLETED6/20/18
FenwayHUNTINGTON AV UNDRPS EBHUNTINGTON AVGAINSBOROUGH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayHUNTINGTON AV UNDRPS WBHUNTINGTON AVHUNTINGTON AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayLONGWOOD AVHUNTINGTON AVBROOKLINE AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
FenwayMEDFIELD STPARK DRBROOKLINE TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkALPHEUS RDBEECH STBATEMAN STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkBEAVER STCLEVELANDDEAD ENDAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/16/18
Hyde ParkBRAEWOOD STAUSTIN STBRAEBURN RDAsphalt ResurfacingMAY2 WEEKSCOMPLETED 5/22/18
Hyde ParkCENTRAL AVARLINGTON STGREENWOOD AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkDAVISON STFAIRMOUNT AVWALTER STAsphalt ResurfacingMAY2 WEEKSCOMPLETED 5/22/18
Hyde ParkERNEST AVWEST MILTON STRIVER STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED / ON HOLD TILL FALL FOR NEW GAS MAIN WORK 
Hyde ParkFAIRMOUNT AVCENTRAL AVTRUMAN PKWY (ODD)Capital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkFAIRMOUNT AVHIGHLAND STSUMMIT STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkGRANTLEY STHYDE PARK AVDEAD ENDFull ReconstructionAPRIL4 MONTHSACTIVE 
Hyde ParkGREENWOOD ST#185HYDE PARK AVEAsphalt ResurfacingMAY-JUNE2 WEEKSCOMPLETED6/8/18
Hyde ParkHADWIN WAYHYDE PARK AVHARDING RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkHUNTINGTON AVTHATCHER STRIVER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkHYDE PARK AV AT DANA AVAT DANA AVSignal Installation WorkTO BE DETERMINED2 MONTHSNOT STARTED 
Hyde ParkHYDE PARK AVAT MILTON STAT MILTON STSignal Installation WorkTO BE DETERMINED3 MONTHSNOT STARTED 
Hyde ParkHYDE PARK AV MILTON STWOLCOT SQUARESidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED 
Hyde ParkLINCOLN STRIVER STHARVARD STCapital ResurfacingTO BE DETERMINED2 WEEKSCOMPLETED5/15/18
Hyde ParkMEADOWVIEW RDSTANBORO STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkMILTON STNEPONSET VALLEY PKWYSPRAUGUE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkMILTON STAT NEPONSET VALLEY PKWYAT NEPONSET VALLEY PKWYSignal Installation WorkTO BE DETERMINED2 MONTHSNOT STARTED  
Hyde ParkMT ASH RD CLEVELAND STDEAD ENDAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/16/18
Hyde ParkNEPONSET VALLEY PKWYAT WOLCOTT SQAT WOLCOTT SQSignal Installation WorkTO BE DETERMINED2 MONTHSNOT STARTED  
Hyde ParkPINGREE STHYDE PARK AVDANA AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkPOYDRAS STRIVER STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkRESERVATION ROADHYDE PARK AVWINTER STSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Hyde ParkSECOND NEW WAY STNOTT ST FAIRMOUNT AVAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/24/18
Hyde ParkSTONEHILL RDALWIN STALWIN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkSTURBRIDGE STRIVER STSANFORD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkTHATCHER STHUNTINGTON AVMETROPOLITAN AVSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Hyde ParkTRACTON AVTILESTON STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkWEBSTER STRIVER STHYDE PARK AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkWESTMINISTER STPROVIDENCE STWESTMINISTER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Hyde ParkWINTER STGLENWOOD STRRESERVATION RDFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Hyde ParkWOLCOTT STWOLCOTT CTRILEY RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTEDACTIVE
Jamaica PlainAVON STPARKSIDE DRBROOKLINE TOWN LINEAsphalt ResurfacingJULY2 WEEKSNOT STARTED 
Jamaica PlainBEECHER STPAUL GORE STBOYLSTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainBILTMORE STCERINA RDCHESTNUT AVEAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/18/18
Jamaica PlainBOURNE STWALK HILL STCANTERBURY STAsphalt ResurfacingJULY2 WEEKSACTIVE 
Jamaica PlainBREWER STBURROUGHS STELIOT STAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/16/18
Jamaica PlainCANTERBURY STMT HOPE STAMERICAN LEG HWY NB LANE (EVEN)Asphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainCATHERINE STBOURNE STFLORIAN STAsphalt ResurfacingJULY2 WEEKSACTIVE 
Jamaica PlainDANFORTH STWYMAN STPAUL GORE STCapital ResurfacingMAY2 WEEKSCOMPLETED5/18/18
Jamaica PlainFORBES STCENTRE STCHESTNUT AVECapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainHALLIDAY STNEPONSET AVEBOURNE STAsphalt ResurfacingJULY2 WEEKSACTIVE 
Jamaica PlainHAMPSTEAD RDARBORWAYDEAD ENDAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/18/18
Jamaica PlainMCBRIDE STSOUTH STLEE STSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
Jamaica PlainMOSS HILL RDSURREYHILL LNSLOCUM RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainOLMSTEAD STFOREST HILLS STPETER PARLEY RDCapital ResurfacingMAY2 WEEKSCOMPLETED5/29/18
Jamaica PlainPERKINS STPRINCE STBROOKLINE TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainPRINCE STPOND ST (80-460)PERKINS STAsphalt Resurfacing2 WEEKS2 WEEKSNOT STARTED 
Jamaica PlainROBINWOOD AVE (1-85)ROBINWOOD AVE(86-110)ENFIELD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainROSEMARY STSOUTH STSPALDING STCapital ResurfacingMAY2 WEEKSCOMPLETED5/29/18
Jamaica PlainSOUTH STARBORWAYBUSSEY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainWASHINGTON STARCHDALE RDBASILE STCapital ResurfacingJUNE2 WEEKSACTIVE/ TRAVEL LANES ONLY/ NEW GAS MAIN NEXT YEAR 
MattapanARBUTUS ST(EVEN)LUCERNE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBALLOU AVEWOODROW AVEJACOB STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanCLARKWOOD ST(EVEN)NORFOLK STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanCOLORADO STMESSINGER STCANAAN STAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/15/18
MattapanCULBERT STWOODHAVEN STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanCUMMINS HWYMT CALVARY RDHARVARD STAsphalt ResurfacingMAY-JUNE2 WEEKSCOMPLETED6/6/18
MattapanEDGEWATER DRRIVER STMATTAKEESET STFull ReconstructionAPRIL1 MONTHCOMPLETED4/24/18
MattapanELLARD RDWOOD AVAYLES RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanKENNEBEC STCUMMINS HWYMARISPOSA STFull ReconstructionAPRIL-MAYONE MONTHCOMPLETED5/14/2018
MattapanLEDGEBROOK RDRIVER STMEADOWBANK AVFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
MattapanLEEHAVEN RDRIVER STMEADOWBANK AVFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
MattapanMEADOWBANK AVRIVER STDEAD ENDFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
MattapanNEWCROFT CIRCLERIVER STRIVER STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
MattapanNORFOLK STWOODROW AVCAPEN STOtherMAY2 WEEKSCOMPLETED/ REPLACED LANE IMPACTED BY NEW GAS MAIN5/23/18
MattapanOUTLOOK RDDUKE STHILLSBORO RDAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/15/18
MattapanRIVER STAT EDGEWATER DRIVEAT EDGEWATER DRIVEIntersection Only WorkJUNE-JULY2 MONTHSNOT STARTED 
MattapanROSEWOOD ST(ODD)RECTOR RDAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/23/18
MattapanRUGBY RD(ODD)BLAKE ST)Capital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanSOUTHMERE RDRIVER STLEDGEBROOK RDFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
MattapanTOPALIAN STRIVER STEDGEWATER DRSidewalk ReconstructionAPRIL-MAY2 MONTHSCOMPLETED4/10/18
North EndHANOVER STCROSS STCOMMERCIAL STAsphalt ResurfacingSEPTEMBER2 WEEKSNOT STARTED/CURRENTLY ALLOWING UTILIY FIBER AND SERVICE CONNECTIONS TO BE DONE OVER THE SUMMER/ PAVING IN SEPTEMBER 
North EndLA FAYETTE AVENDICOTT STPRINCE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndMICHELANGELO STDILLAWAY PLDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndMOON STNORTH SQUARE LEWIS STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED  
North EndNORTH SQPRINCE STMOON STFull ReconstructionJUNE THROUGH NOVEMBER6 MONTHSACTIVE 
North EndNORTH STCLARK STCOMMERCIAL STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndWIGET STSALEM STNORTH MARGIN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleALPHEUS RDBEECH STBATEMAN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleAMHERST STBELGRADE AVPENFIELD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleBELGRADE AVSOUTH STROBERT STCapital ResurfacingTO BE DETERMINED2 WEEKSCOMPLETED4/26/18
RoslindaleBERYL STCORNELL STALDRICH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
RoslindaleBIRCH STCORINTH STDURNELL STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
RoslindaleBIRCH STBELGRADE AVECORINTH STCapital ResurfacingAPRIL2 WEEKSCOMPLETED4/26/18
RoslindaleCANTERBURY STBOURNE STNEPONSET AVSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
RoslindaleCOHASSETT STCORINTH STALBANO STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleCORINTH STROBERT STWASHINGTON STCapital ResurfacingAPRIL2 WEEKSCOMPLETED4/29/18
RoslindaleHILLOCK STBERYL STCORNELL STFull ReconstructionAPRIL- JULY4 MONTHSACTIVE 
RoslindaleKITTERDGE STAT WHITFORD STAT WHITFORD STSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
RoslindaleMELCALF STPENFIELD STDURNELL AVEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindalePOPLAR STSOUTH STWASHINGTON ST STCapital ResurfacingAPRIL2 WEEKSCOMPLETED4/29/18
RoslindaleROBERT STCORINTH STBROOKFIELD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleROWE STBROWN AVCUMMINS HWYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleSOUTH STWASHINGTON STBELGRADE AVCapital ResurfacingAPRIL2 WEEKSCOMPLETED4/29/18
RoslindaleSOUTH STAT BUSSEY STAT BUSSEY STSidewalk ReconstructionJULY- OCTOBER4 MONTHSNOT STARTED 
RoslindaleWASHINGTON STSOUTH STPOPLAR STCapital ResurfacingAPRIL2 WEEKSCOMPLETED4/29/18
RoxburyALLERTON STGERARD STPIERSON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyBETHUNE WAYZEIGLER STEUSTIS STAsphalt ResurfacingTBDTBDNOT STARTED 
RoxburyBROOK MARSHALL RDRUGGLES STSOJOURNER TRUTH CTFull ReconstructionMAY-AUGUST4 MONTHSACTIVE 
RoxburyCAMDEN STCOLUMBUS AVENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
RoxburyCEDAR STCOLUMBUS AVTERRACE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyDEWITT DRKERR PLSHAWMUT AVFull ReconstructionMAY- AUGUST4 MONTHSACTIVE 
RoxburyDORR STHIGHLAND STLAMBERT AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyDUBOIS STORCHARD PK STADAMS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyDUDLEY STWARREN STWINSLOW STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED/DEVELOPMENT AND UTILITY WORK MAY DELAY UNTIL 2019 
RoxburyDUDLEY STMAGAZINE STEAST COTTAGE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED/DEVELOPMENT AND UTILITY WORK MAY DELAY UNTIL 2019 
RoxburyEAST LENOX STHARRISON AVWASHINGTON STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED 
RoxburyESTABROOK RDSHAWMUT AVDEWITT DRFull ReconstructionTBDTBDNOT STARTED 
RoxburyHARRISON AVMELNEA CASS BLVDEAST LENOX STSidewalk ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
RoxburyJUNIPER TERJUNIPER STWASHINGTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyKERR PLDEWITT DRSOJOURNER TRUTH CTFull ReconstructionJUNE- AUGUST1 MONTHNOT STARTED 
RoxburyKERR WAYRUGGLES STKERR PLFull ReconstructionMAY- AUGUST4 MONTHSACTIVE 
RoxburyMALCOM X BLVDAT KING STAT KING STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED 
RoxburyMT PLEASANT AVDUDLEY STDUDLEY STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyNEWCOMB STHARRISON AVWASHINGTON STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
RoxburyNORTHAMPTON STALBANY STHARRISON AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyNORTHAMPTON STTREMONT STCOLUMBUS AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyRAYNOR CIRBROOK MARSHALL RDRUGGLES STFull ReconstructionMAY-AUGUST4 MONTHSACTIVE 
RoxburyREED STEAST LENOX STENDFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
RoxburyRITCHIE STCOLUMBUS AVMARCELLA STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
RoxburyRUGGLES ST ESHAWMUT AVTREMONT STFull ReconstructionTBD4 MONTHSNOT STARTED 
RoxburySHAWMUT AVMELNEA CASS BLVDMADISON PARK CTSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED 1 SIDE 
RoxburySOJOURNER TRUTH CTKERR PLACEMELNEA CASS BLVDFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED 
RoxburySTOCKWELL STWAIT STHUNTINGTON AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyTHORNDIKE STHARRISON AVWASHINGTON STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
RoxburyWAIT STHUNTINGTON AVDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyWAKULLAH STROCKLAND STDALE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyWAUMBECK STHUMBOLDT AVCRAWFORD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyWIGGLESWORTH STTREMONT STHUNTINGTON AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyWILLIAMS STEUSTIS STSHAWMUT AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonA.VARIOUSA.VARIOUSA.VARIOUSOtherMAY1 MONTHACTIVE/ PATCH PAVING OF PREVIOUS UTILITY CUTS ON VARIOUS SOUTH BOSTON STREETS/ PHASE 1. SAW CUT PATCHES./PHASE 2 DIG LEAVE DOWN 1.5" IN BINDER / PHASE 3. TOP WITHIN 3 DAYS 
South BostonBECKLER AVK STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonD STWEST FIRST STSUMMER STAsphalt ResurfacingAPRIL2 WEEKSCOMPLETED4/22/18
South BostonDRESSER STE STDORCHESTER STCapital ResurfacingTO2 WEEKSNOT STARTED 
South BostonEAST NINTH STWEST NINTH STMERCER STAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/11/18
South BostonEAST SECOND STH STK STAsphalt ResurfacingAUGUST-SEPTEMBER2 WEEKSNOT STARTED/ PAVING BY EVERSOURCE  
South BostonEAST SECOND STK STM STCapital ResurfacingJUNE2 WEEKSCOMPLETED6/5/18
South BostonEMERSON STL STM STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonG STDORCHESTER STEAST BROADWAYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonH STCOLUMBIA RDEAST SECOND STAsphalt ResurfacingSEPTEMBER2 WEEKSNOT STARTED/ PAVING BY EVERSOURCE  
South BostonJAY STEAST FIFTH STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonN ST933EAST BROADWAYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonNORTHERN AVSEAPORT BLVD#75 NORTHERN AVPIC ResurfacingJULY -NOVEMBER5 MONTHSNOT STARTED/ DEVELOPER TO RESURFACE LATE SUMMER FALL 
South BostonSANGER STEAST SEVENTH STEAST EIGHTH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonSEAPORT BLVDATLANTIC AVNORTHERN AVPIC ResurfacingJULY- NOVEMBER5 MONTHSNOT STARTED/ DEVELOPER TO RESURFACE LATE SUMMER FALL 
South BostonSLEEPER STNORTHERN AVSEAPORT BLVDPIC ReconstructionJULY -NOVEMBER5 MONTHSNOT STARTED/ DEVELOPER TO RESURFACE LATE SUMMER FALL 
South BostonSUMMER STEAST SEVENTH STEAST EIGHTH STSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
South BostonSUMMER STMELCHER STWEST SERVICE RDFull ReconstructionAPRIL- JULY4 MONTHSACTIVE  
South BostonVICKSBURG STEAST FIRST STEAST SECOND STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonWEST NINTH STD STE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonWEST SECOND STA STB STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
South EndBERKELEY STTREMONT STCOLUMBUS AVFull ReconstructionJUNE - NOVEMBER5 MONTHSACTIVE / WAITING FOR UTILITY WORK TO BE DONE BEFORE PAVING 
South EndBRADFORD STWALTHAM STMILFORD STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndCOLUMBUS AVMASS AVTREMONT STAsphalt ResurfacingJUNE- JULY2 WEEKSNOT STARTED 
South EndDEACON STWORCESTER STWEST CONCORD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndEAST BERKELEY STTREMONT STCOLUMBUS AVFull ReconstructionAUGUST 2016JULYRECONSTRUCTION/ACTIVE 
South EndHARRISON AVHERALD STEAST BERKELEY STSidewalk ReconstructionTO BE DETERMINEDTO BE DETERMINEDNOT START  
South EndMARGINAL RDSHAWMUT AVARLINGTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndPAUL PLACESHAWMUT AVHERALD STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
South EndPAUL SULLIVAN WAYHARRISON AVALBANY STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
South EndRUTLAND SQTREMONT STCOLUMBUS AVCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED/ COORDINATING UTILITY WORK FIRST BEFORE PAVING 
South EndRUTLAND STSHAWMUT AVRUTLAND SQCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndWEST SPRINGFIELD STTREMONT STCOLUMBUS AVAsphalt ResurfacingTBDTBDNOT STARTED 
West RoxburyACACIA RDCENTRE STANSONIA RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyALWARD RDWELD STBUCHANAN RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyATWILL RDPARK STRICHWOOD STAsphalt ResurfacingJULY2 WEEKSNOT STARTED 
West RoxburyBUCHANAN RDPRESIDENT RDBURRWOOD RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyCENTRE STMT VERNON STELGIN STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyCHAPIN STMT VERNON STPRESTON RDFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
West RoxburyCOREY STVFW PARKWAYFURBUSH RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyCOREY STFURBUSH RDNEWTON TOWN LINECapital ResurfacingJULY2 WEEKSCOMPLETED7/5/18
West RoxburyCOREY STPARK STRAILROAD STFull ReconstructionMAY-AUGUST4 MONTHSNOT STARTED 
West RoxburyCROSSTOWN AVSALMAN STDEDHAM TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyCURLEW STMAPLEWOOD STENDFull ReconstructionMAY-AUGUST4 MONTHSACTIVE 
West RoxburyCYPRESS STBAKER STSPRING STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyDUNWELL STBAKER STHELDUN STCapital ResurfacingTBDTBDNOT STARTED 
West RoxburyFRANCESCA STVERMONT STKEITH STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyFURBUSH RDLA GRANGE STCOREY STCapital ResurfacingMAY2 WEEKSCOMPLETED5/14/18
West RoxburyHEMLOCK RD GOULD STCALEDONIAN AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyHILCREST STELGIN STTEMPLE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyJACQUELINE RDANSONIA RDBIRCHLAND AVFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
West RoxburyJESHURUN STGROVE STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyKEANE RDVFW PARKWAYBROOK FARM RDCapital ResurfacingJULY2 WEEKSCOMPLETED7/5/18
West RoxburyKIERNAN RDVFW PARKWAYDEAD ENDCapital ResurfacingJULY2 WEEKSCOMPLETED7/5/18
West RoxburyKIRK STMONTVIEW STFERNCROFT RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyLAGRANGE STAT BELLEVUE HILL RDAT BELLEVUE HILL RDSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET. ADVERTISED LATE 2018/ LIKELY 2019 START 
West RoxburyLAGRANGE STCENTRE STVFW PARKWAYAsphalt ResurfacingTBDTBDNOT STARTED 
West RoxburyLANDSEER STBELLEVUE STLA GRANGE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyLOYOLA CIRLAGRANGE STDEAD ENDAsphalt ResurfacingMAY2 WEEKSCOMPLETED 5/16/2018
West RoxburyMARLIN RDCOREY ST DEAD ENDCapital ResurfacingMAY2 WEEKSCOMPLETED 5/18/18
West RoxburyMEREDITH STKENNETH STCLEMENT AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyNEWFIELD STVFW PARKWAYBROOK FARM RDCapital ResurfacingJULY2 WEEKSCOMPLETED7/7/18
West RoxburyPELTON STWEST ROXBURY SURFACE PKWYWEST ROXBURY PARKWAYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyRAILROAD STCOREY ST380' E OF COREY STFull ReconstructionJUNE- SEPTEMBER4 MONTHSNOT STARTED  
West RoxburyREDLANDS RDCENTRE STALAMEDA RDAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/15/18
West RoxburyRISLEY RDHACKENSACK RDBROOKLINE TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburySHERBROOK STLA GRANGE STDENT STAsphalt ResurfacingJULY2 WEEKSNOT STARTED 
West RoxburySTEARNS RDWASHINGTON STDEAD ENDAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/24/18
West RoxburySUNSET HILL RDSUNSET HILL PATHDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyVARICK RDTEMPLE STBAKER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyVERMONT STLA GRANGE STBAKER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyWEST BOUNDRY RDGEORGETOWNE DRWASHINGTON STAsphalt ResurfacingJUNE- JULY2 WEEKSACTIVE 
         
 