City of Boston
 
 
Public Works Department
Contact Us
 
City Departments
Resurfacing By Neighborhood And Street

You can find a working list of streets below that the City of Boston plans on resurfacing or reconstructing during the 2020 construction season. This list is subject to change and may be altered to accommodate necessary underground infrastructure improvements or other unforeseen circumstances.

If you live on a street that is proposed for resurfacing or reconstruction and are thinking about installing a new service or upgrading a current service for your building, it is critical that you refer to our utilities fact sheet

Any delay may result in the street being paved and your ability to receive a permit for a service connection denied.

We created a page to explain the resurfacing process in more detail. If you have any questions, please contact the Construction Management division of Public Works at 617-635-4950.


Search By:     Or By:
NeighborhoodStreetFrom StreetTo StreetWork TypeEstimated StartDurationStatusCompleted
Allston/BrightonALLSTON STSERVICE RD (OFF COMM AV WB)BELLVISTA RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonBOSTONIA AVBRECK AVDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonBRECK AVWASHINGTON STBRAYTON RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonBURTON STWASHINGTON STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonCAMBRIDGE STLINCOLN ST- WINDOM STPED RAMP UPGRADE/NEW SIGNALSIntersection Only WorkTO BE DETERMINED3 WEEKSNOT STARTED 
Allston/BrightonCENACLE RDLAKE STWILLOUGHBY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonCHESTNUT HILL AV@ WINSHIP STNASidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED  
Allston/BrightonCHESTNUTHILL AVBEACON STCOMMONWEALTH AVSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED 
Allston/BrightonEGREMONT RDCUMMINGS RDMT HOOD RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonFANEUIL STMARKET STWASHINGTON STCapital ResurfacingJULY2 WEEKSNOT STARTED 
Allston/BrightonFISKE TERRBRAINERD RDBROOKLINE TOWN LINECapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonGARDENA STGLENCOE STDUSTIN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonGLENMONT RDWILLOUGHBY STLAKE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonGORDON STCAMBRIDGE STCAMELOT CTAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonGUILFORD STSAUNDERS STPOMEROY STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonHARVARD AVSERVICE RD (OFF COMM AV WB)BROOKLINE TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonHIGH ROCK WYIMRIE RDGORDON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonIMRIE RDCAMBRIDGE ST BRDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonLEICESTERWASHINGTON ST BRSURREY STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonLONG AVSERVICE RD (OFF COMM AV WB)ALLSTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonMT VERNON ST BRACADEMY HILL RD FOSTER ST BRFull ReconstructionTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonPOMEROY STGORDON STSAUNDERS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonPOMFRET ST MAPLE ST WRCOREY ST WRCapital ResurfacingAUGUST2 WEEKSCOMPLETED8/7/2020
Allston/BrightonRYDER HILL RDBRAYTON RDDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonSOLDIER FIELD PLSOLDIERS FIELD RDDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonWADE STCOMMONWEALTH AV EB LN (EVEN)DEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonWASHINGTON STMONASTERY RDSNOW STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonWASHINGTON STSNOW STCAMBRIDGE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonWESTBOURNE TRBROOKLINE TOWN LINECOREY RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Allston/BrightonWILSHIRE RDCHESTNUT HILL AVDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED  
Back BayARLINGTON STISABELLA STMELROSE STSidewalk ReconstructionJUNE3 MONTHSACTIVE 
Back BayARLINGTON ST BPBOYLSTON ST BPCOLUMBUS AV NAsphalt ResurfacingMAY2 WEEKSNOT STARTED6/13/20
Back BayBEACON STAT BERKELEY STPED RAMP UPGRADE/NEW SIGNALSIntersection Only WorkTO BE DETERMINED3 WEEKSNOT STARTED 
Back BayBEACON STARLINGTON STMASS AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BayBERKELEY STCOMMONWEALTH AV WB (ODD)BEACON STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BayDARTMOUTH STAT MARLBOROUGH STPED RAMP UPGRADE/NEW SIGNALSIntersection Only WorkTO BE DETERMINED3 WEEKSNOT STARTED 
Back BayEXETER STBOYLSTON ST BPBLAGDEN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BayMARLBOROUGH STARLINGTON ST BPBERKELEY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BayNEWBURY STDARTMOUTH STEXETER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BayNEWBURY STCLARENDON STDARTMOUTH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BayPROVIDENCE STARLINGTON STBERKELEY STAsphalt ResurfacingJUNE2 WEEKSCOMPLETED6/13/20
Back BayPUBLIC ALLEY 401PUBLIC ALLEY 402 HARCOURT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BayST JAMES AVBERKELEY STCLARENDON STAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/27/20
Back BaySTANHOPE STBERKELEY STTRINITY PLAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Back BaySTUART STBERKELEY STCLARENDON STAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/27/20
Back BaySTUART STTREMONT STCHARLES ST SOUTHAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/21/20
Back BayTREMONT ST RX BPBOYLSTON ST BPMARGINAL RDAsphalt ResurfacingMAY-JUNE2 WEEKSCOMPLETED6/6/20
Back BayWESTLAND AVMASS AV- HEMENWAYPED RAMP UPGRADE/NEW SIGNALSIntersection Only WorkTO BE DETERMINED3 WEEKSNOT STARTED 
Beacon HillBEACON STPRESCOTT STWOLCOTT CTFull ReconstructionTO BE DETERMINED2 WEEKSNOT STARTED 
Beacon HillRIDGEWAY LNCAMBRIDGE ST BRDERNE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Beacon HillRIVER ST BPBEACON ST BPCHESTNUT ST BPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Beacon HillTEMPLE STDERNE STCOOLIDGE AVPIC ResurfacingSEPTEMBER2 WEEKS  
Boston ProperBATTERYMARCH STWATER ST BPHIGH ST BPAsphalt ResurfacingMAY-JUNE2 WEEKSCOMPLETED5/6/20
Boston ProperCHAUNCY STSUMMER STBEDFORD STAsphalt ResurfacingJULY2 WEEKSCOMPLETED7/9/20
Boston ProperFRANKLIN ST BPHAWLEY ST SARCH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Boston ProperPARK STTREMONT ST BEACON STFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
Boston ProperSUMMER ST BPHAWLEY ST SATLANTIC AV BPAsphalt ResurfacingJULY2 WEEKSACTIVE7/9/20
Boston ProperWENDELL STBATTERYMARCH STBROAD STAsphalt ResurfacingMAY2 WEEKSCOMPLETED5/26/20
CharlestownCARTER STCAMBRIDGE ST CHROLAND STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownCORDIS STWARREN STHIGH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownELLWOOD STPUTNAM STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownFIFTH STCHELSEA STFIRST AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownHENLEY STHARVARD SQWARREN ST CHCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownLYNE ROADUNION ST DEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownNINTH STTHIRD AVFIRST AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownPUTNAM STDEAD ENDCOMMON STAsphalt ResurfacingTO BE DETERMINEDTWO WEEKSNOT STARTED 
CharlestownRUTHERFORD AVUNION ST DEVENS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownTHIRD AVTHIRTEENTH STSIXTHTEENTH STAsphalt ResurfacingTO BE DETERMINEDTWO WEEKSNOT STARTED 
CharlestownWASHINGTON STHARVARD STRUTHERFORD AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
CharlestownWOOD STMAIN STHIGH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
ChinatownBAIRD STMORTON STBLUE HILL AVCapital ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/10/2020
DorchesterALVAN TRSUMNER STDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBALINA PLNORFOLK ST DODEAD ENDCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
DorchesterBANTON STDORCHESTER AVDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBELDEN STBELDEN SQHOLDEN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBELDEN STHOLDEN STHUMPHREYS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBLUE HILL AVWASHINGTON STGLENWAY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBLUE HILL AVCHENEY STGLEN LANEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBLUE HILL AVGLEN LANEAMERICAN LEGION HIGHWAYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterBOWDOIN STADAMS STHANCOCK STFull ReconstructionMARCH-JUNE3 MONTHSCOMPLETED6/6/2020
DorchesterBRENT STTALBOT AVMELBOURNE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterCARLOTTA STCENTRE STDEAD ENDAsphalt ResurfacingJUNE2 WEEKSCOMPLETED6/16/20
DorchesterCENTERVALE PKUPLAND AVBOURNESIDE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterCENTRE STDORCHESTER AVCENTRE AVAsphalt ResurfacingJUNE2 WEEKSCOMPLETED6/16/20
DorchesterCLEMATIS STCENTRE STWHITTEN STAsphalt ResurfacingJUNE/JULY2 WEEKSCOMPLETED7/2/20
DorchesterDAKOTA STWASHINGTON STCLAYBOURNE STCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
DorchesterDAWSON STMSGR LYDON WAYMALLET STCapital ResurfacingJUNR/JULY2 WEEKSCOMPLETED6/18/20
DorchesterDORCHESTER AVWELLES AVTALBOT AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterDORCHESTER AVAT LINDEN STAT LINDEN STFull ReconstructionTO BE DETERMINED2 MONTHSACTIVE3/04/2020
DorchesterDORCHESTER AVAT BAILEY STAT BAILEY STSidewalk ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
DorchesterDORCHESTER AV DOVON HILLERN STHOWELL STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterEAST COTTAGE ST HUMPHREYS STNORFOLK AVSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET 
DorchesterEAST STCHURCH STADAMS STFull ReconstructionMARCH - JULY3 MONTHSCOMPLETED6/25/2020
DorchesterEDWIN STDORCHESTER AV DOFLORIDA STCapital ResurfacingJUNE/JULY2 WEEKSCOMPLETED6/18/20
DorchesterELM LAWN STCENTRE STDEAD ENDAsphalt ResurfacingJUNE/JULY2 WEEKSCOMPLETED7/2/20
DorchesterELY RDFREDERIKA STKENMARE RDAsphalt ResurfacingJULY2 WEEKSCOMPLETED7/15/20
DorchesterEPPING STWASHINGTON STNORFOLK STAsphalt ResurfacingJULY2 WEEKSNOT STARTED 
DorchesterERIE ST DOELLINGTON STGLENWAY STCapital ResurfacingJULY2 WEEKSACTIVE 
DorchesterEUCLID STWITHINGTON STWASHINGTON STFull ReconstructionTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterFLORIDA STLONSDALE STMSGR LYDON STCapital ResurfacingJUNE/JULY2 WEEKSCOMPLETED6/18/20
DorchesterGENE STHUMPHREYS STBELDEN STAsphalt ResurfacingJULY2 WEEKSACTIVE 
DorchesterGENEVA AVCHARLES STWALDECKFull ReconstructionTO BE DETERMINED3 MONTHSCOMPLETED3/4/2020
DorchesterGINITA STCENTRE STDEAD ENDAsphalt ResurfacingJUNE2 WEEKSCOMPLETED6/16/20
DorchesterGRANVILLE STGALLIVAN BLVDMILTON ST DOCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterHANCOCK STBOWDOIN STHIGH STFull ReconstructionFEBRUARY-MARCH1 MONTHCOMPLETED3/21/2020
DorchesterHARVARD ST AT SCHOOL ST AND THANE STPED RAMP UPGRADE/PLUS PAVINGIntersection Only WorkTO BE DETERMINED3 WEEKSNOT STARTED 
DorchesterHEWINS STCOLUMBIA RDERIE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterHIGH STCHURCH STHANCOCK STFull ReconstructionFEBRUARY-MARCH1 MONTHCOMPLETED3/21/2020
DorchesterHOPESTILL STASPINWALL RDSOUTHERN AVCapital ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/16/2020
DorchesterHOUGHTON STVICTORY RDPOPES HILL STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterKEVIN RDSUMNER STDEAD ENDAsphalt ResurfacingJULY2 WEEKSACTIVE 
DorchesterLOMBARD STBUSHNELL STCARRUTH STAsphalt ResurfacingSEPTEMBER2 WEEKSACTIVE 
DorchesterLORENZO STWOODWORTH STWALNUT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterMALLET STADAMS ST DO NFLORIDA STCapital ResurfacingJUNE/JULY2 WEEKSACTIVE 
DorchesterMATHER STNIXON STLYNDHURST STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterMELLEN STOCEAN STMONTAGUE STAsphalt ResurfacingJULY2 WEEKSCOMPLETED7/16/20
DorchesterMOODY STTORREY STDUNBAR AVAsphalt ResurfacingJULY2 WEEKSCOMPLETED7/16/20
DorchesterMSGR LYDON WAYFLORIDA STADAMS ST DO NCapital ResurfacingJUNE/JULY2 WEEKSCOMPLETED7/15/20
DorchesterMT BOWDOIN GREENBOWDOIN AVMALLON RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterNEW ENGLAND AVTALBOT AVWOODROW AVFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
DorchesterNORFOLK STWHITFIELD STEPPING STSidewalk ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED/GREEN INFRASTRUCTURE AT EPPING ST 
DorchesterNORTH MONROE TERRNEPONSET AV DOTRAIN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterNOTTINGHAM STBOWDOIN AVBULLARD STAsphalt ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
DorchesterOLD RDMICHIGAN AVCOLUMBIA RDSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED YET 
DorchesterPARK STAT NORWELL STPED RAMP UPGRADE/PLUS PAVINGIntersection Only WorkJULY2 WEEKSNOT STARTED 
DorchesterPARK ST DOGREENBRIER STWASHINGTON ST DOCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterQUINCEFIELD STHUMPHREYS STWENDOVER STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED  
DorchesterREMINGTON STNIXON STCENTRE ST DOAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterRICHFIELD STCOLUMBIA RDPURITAN AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterROSSETER STELDON STBOWDOIN AVAsphalt ResurfacingJULY2 WEEKSACTIVE 
DorchesterSCHOOL ST DOWASHINGTON ST DOHARVARD ST DOCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterSOUTHERN AVAT WHIFIELD STPED RAMP UPGRADE/PLUS PAVINGIntersection Only WorkTO BE DETERMINED3 WEEKSNOT STARTED 
DorchesterSUMNER PKSUMNER STDEAD ENDCapital ResurfacingJULY2 WEEKSNOT STARTED 
DorchesterTALBOT AVAT COLONIAL AVPED RAMP UPGRADE/PLUS PAVINGIntersection Only WorkTO BE DETERMINED3 WEEKSNOT STARTED 
DorchesterTILMAN STDORCHESTER AVDEAD ENDCapital ResurfacingSEPTEMBER2 WEEKSACTIVE 
DorchesterVIRGINIA STDUDLEY STBIRD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWASHINGTON STBRENT STEUCLID STFull ReconstructionTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWASHINGTON STERIE STHARVARD STAsphalt ResurfacingJULY2 WEEKSNOT STARTED 
DorchesterWASHINGTON STTALBOT AVEPPING STFull ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED 
DorchesterWASHINGTON STBLUE HILL AVCOLUMBIA RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWASHINGTON STCOLUMBIA RDERIE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
DorchesterWHITTEN STDORCHESTER AVADAMS STAsphalt ResurfacingJUNE2 WEEKSCOMPLETED6/15/20
DorchesterWOLCOTT STCOLUMBIA RDERIE STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonBENNINGTON STMERIDIAN STLONDON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonBENNINGTON STLONDON STPRESCOTT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonBENNINGTON STSWIFT ST425 E OF WORDSWORTH STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonCHELSEA STMAVERICK STGEORGE R VISCONTI RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonCRESTWAY RDFAYWOOD AVWALDEMAR AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonMERIDIAN STWHITE STMCARDLE, ANDREW P BRIDGECapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonMERIDIAN STAT LONDON STAT LONDON STSignal Installation WorkAPRIL-JUNE3 MONTHSACTIVE6/15/2020
East BostonNEPTUNE RDSARATOGA STBENNINGTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonSARATOGA STTRIDENT ST165' E OF TRIDENT STSidewalk ReconstructionTO BE DETERMINED2 WEEKSSIDEWALK RECON 
East BostonSUMNER STMAVERICK SQORLEANS STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
East BostonTRIDENT STSARATOGA STBENNINGTON STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED 
East BostonWHITE STBORDER STBROOKS STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayCOMMONWEALTH AVCHARLESGATE WEST350' E OF BEACON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayKESWICK STMEDFIELD STBEACON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayST ALBANS RDFRANCIS STHUNTINGTON AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwaySTONEHOLM STNORWAY STEDGERLY RDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
FenwayTETLOW STEVANS WAYPALACE RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkBEACON STFAIRMOUNT AVMILTON TOWN LINEAsphalt ResurfacingAUGUST2 WEEKSCOMPLETED8/22/2020
Hyde ParkCOLLINS ST HYDE PARK AV BRADLEE ST HPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkCOMO RDREADVILLE STERNEST AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkEDITH STBEACON STMETROPOLITAN AVAsphalt ResurfacingAUGUST2 WEEKSCOMPLETED8/22/2020
Hyde ParkEDSON ST HPNORTON ST HPCHESTERFIELD STCapital ResurfacingAUGUST2 WEEKSCOMPLETED8/17/2020
Hyde ParkHYDE PARK AV AT DANA AVFull ReconstructionAPRIL -JUNE3 MONTHSNOT STARTED3/04/2020
Hyde ParkPLEASANT STVOSE AVMETROPOLITAN AVAsphalt ResurfacingAUGUST2 WEEKSCOMPLETED8/21/2020
Hyde ParkREADVILLE STWEST MILTON STNEPONSET VALLEY PKWYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkRESERVATION ROADHYDE PARK AVWINTER STSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED  
Hyde ParkREYNOLD RDCHESTERFIELD STCOMO RDAsphalt ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
Hyde ParkROXANA STRIVER ST HPSUNNYSIDE ST HPCapital ResurfacingAUGUST2 WEEKSCOMPLETED8/17/2020
Hyde ParkTHATCHER STHUNTINGTON AVMETROPOLITAN AVFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
Hyde ParkWESTMINSTER STPROVIDENCE STMETROPOLITAN AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Hyde ParkWINTER STGLENWOOD STRESERVATION RDSidewalk ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED YET 
Jamaica PlainARCOLA STDAY STDEAD ENDCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainASHLEY STCHESTNUT STARMSTRONG STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainBISHOP STNEWBERN STEVERETT ST JPCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainCANTERBURY STAMERICAN LEGION HIGHWAYBOURNE STSidewalk ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
Jamaica PlainCASTLETON STSOUTH HUNTINGTON AVJAMAICA WAYCapital ResurfacingAUGUST2 WEEKSCOMPLETED8/17/2020
Jamaica PlainCHESTNUT SQCHESTNUT AVGLENVALE TRCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainGLENVALE TERRACELAMARTINE STCHESTNUT SQAsphalt ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
Jamaica PlainHYDE PARK AVWASHINGTON STUKRAINE WAYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainLAKEVILLE RDCENTRE ST WR JP RXBEAUFORT RDCapital ResurfacingAUGUST/SEPTEMBER2 WEEKSCOMPLETED8/31/2020
Jamaica PlainNIRA AVDAY STGROTTO GLEN RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainPARKTON RDPERKINS STPERKINS STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainPERKINS STPRINCE STBROOKLINE TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainPOND VIEW AVPERKINS ST JPPERSHING RDCapital ResurfacingAUGUST/SEPTEMBER2 WEEKSNOT STARTED 
Jamaica PlainROBINWOOD AVROBINWOOD AVLOCKSLEY STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainSTELLMAN RDWASHINGTON STFAWNDALE RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Jamaica PlainWALDEN STHEATH STCENTRE ST WR JP RXCapital ResurfacingAUGUST2 WEEKSCOMPLETED8/14/2020
Jamaica PlainWESTERLY STCENTRE STSUNNYSIDE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBANGELL STGREENOCK STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBMORTON ST DO JPFREMONT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBGREENOCK STRHOADES STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBREXFORD STRIVER ST HPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBRHOADES ST WOODHAVEN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBWOODHAVEN STREXFORD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBFREMONT STBABSON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBHARVARD ST DOMORTON ST DO JPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanBLUE HILL AV NBBABSON STRIVER ST HPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanCOOKSON TERRACEBABSON STMEROLA PKAsphalt ResurfacingJULY2 WEEKSCOMPLETED7/16/20
MattapanEDGEWATER DRATRIVER STFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
MattapanFESSENDON STBLUE HILL AV NBNORFOLK ST DOCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
MattapanFOTTLER RDWALK HILL STMATTAPAN STCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED9/14/2020
MattapanFRENCH STDELHI STVIOLET STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanGROVELAND STRIVER STMARYKNOLL STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
MattapanIRMA STCALLENDER STWOODROW AVAsphalt ResurfacingJULY2 WEEKSCOMPLETED7/16/20
MattapanLEAHAVEN RDRIVER STMEADOWBANK AVFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
MattapanNEWCROFT CRRIVER STRIVER STFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
MattapanRITCHIE STRIVER STDEAD ENDFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
MattapanSELDEN STMILTON AVMORTON STAsphalt ResurfacingJUNE/JULY2 WEEKSCOMPLETED7/2/20
MattapanSOUTHMERE RDRIVER STLEDGEBROOK RDFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
MattapanTESLA STRIVER STEDGEWATER DRCapital ResurfacingJULY2 WEEKSCOMPLETED7/16/20
MattapanWOODROW AVBALLOU AVWOLLASTON TRAsphalt ResurfacingJULY2 WEEKSCOMPLETED7/17/20
MattapanWOOLSON STBLUE HILL AVNORFOLK STCapital ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/14/2020
Mission HillHARLESTON STCALUMET STPARKER HILL AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
Mission HillPARKER HILL AVHUNTINGTON AVPARKER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndCHARTER STHENCHMEN STCOMMERCIAL STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndCOOPER STSALEM STNORTH WASHINGTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndENDICOTT STTHACHER STNORTH WASHINGTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndGARDEN COURT STPRINCE ST BPFLEET ST BPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndHULL STSALEM STCOMMERCIAL STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndMICHELANGELO STCHARTER ST DEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndSALUTATION STHANOVER ST BP NCOMMERCIAL ST BP NAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndSUN CT STNORTH SQNORTH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
North EndWIGET STSALEM STNORTH MARGIN STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleBEECH STEUGENIA RDWASHINGTON STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleBROOKWAY RDALDWIN RDARCHDALE RDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoslindaleSHELDON STPROSPECT AVCUMMINS HYAsphalt ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/11/2020
RoxburyANITA TERRACEROXBURY ST138' SW OF ROXBURY STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyBALL ST SHAWMUT AVWASHINGTON STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyBENTON STTREMONT ST RX BPCOLUMBUS AV NCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyBLANCHARD STBARTLETT ST RXNORFOLK ST RXCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
RoxburyDAVENPORT STTREMONT ST RX BPCOLUMBUS AV NCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
RoxburyDUDLEY STWARREN STWASHINGTON STFull ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED / DUDLEY SQ 
RoxburyDUDLEY TERRDUDLEY STDEAD ENDAsphalt ResurfacingJULY2 WEEKSNOT STARTED 
RoxburyDUNMORE STDUDLEY STMAGAZINE STCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
RoxburyELMORE STKENSINGTON STWALNUT AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyGEORGE STMAGAZINE STSHIRLEY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyGUILD ROWMALCOLM X BLVDWASHINGTON STFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
RoxburyHARRISON AVZEIGLER STWARREN STFull ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED 
RoxburyKEMBLE STGERARD STMAGAZINE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyMALCOLM X BLVDDUDLEY ST100' W OF SHAWMUT AVFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
RoxburyMAPLE STGEORGIA STSEAVER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyMASSACHUSETTS AVPROCTOR STNAPA STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyPARKER STFISHER AVHEATH SQ ROTARYAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyPARKER ST RXHEATH STBICKFORD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyREED STNORTHAMPTON STEAST LENOX STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyREGENT STCIRCUIT STDALE ST RXCapital ResurfacingJULY2 WEEKSACTIVE 
RoxburyRITCHIE STCOLUMBUS AVMARCELLAFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
RoxburyROCKVILLE PK EWARREN ST RX NBDEAD ENDCapital ResurfacingJULY2 WEEKSACTIVE 
RoxburyROXBURY STMALCOM X BLVDWASHINGTON STFull ReconstructionTO BE DETERMINED6 MONTHSNOT STARTED /DUDLEY SQ 
RoxburyRUGGLES ST ETREMONT STWASHINGTON STFull ReconstructionTO BE DETERMINED4 MONTHSNOT STARTED 
RoxburySHAWMUT AVMALCOLM X BLVD150' N OF MALCOLM X BLVDFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
RoxburySHERMAN STROCKLAND STDALE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburySOUTHAMPTON STMASSACHUSETTS AVDORCHESTER AV DOAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyTOWNSEND ST RXWALNUT AVCRESTWOOD PKCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
RoxburyWABON STWARREN ST RX ONE LN SWABENO STCapital ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
RoxburyWAKULLAH STROCKLAND ST RXDALE ST RXCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
RoxburyWARREN STPALMER STDUDLEY STFull ReconstructionTO BE DETERMINED6 MONTHSNOT STARTED DUDLEY SQ 
RoxburyWARREN STDUDLEY STKEARSARGE AVFull ReconstructionAPRIL6 MONTHSNOT STARTED/ DUDLEY SQ 
RoxburyWASHINGTON STDUDLEY STRUGGLES STFull ReconstructionTO BE DETERMINED6 MONTHSNOT STARTED DUDLEY SQ 
RoxburyWESTMINSTER AVWASHINGTON STWALNUT AVAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonCARPENTER STDEVINE, WILLIAM H WYPREBLE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonD STWEST BROADWAYWEST FIRST ST SAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonDORCHESTER AVDEVINE, WILLIAM H WYKEMP STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonDRESSER STE STF STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonDRESSER STF STDORCHESTER STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonEAST FIFTH STG STH STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonGREENBAUM STDORCHESTER AVFOUNDRY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonH STEAST BROADWAYEAST SIXTH STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonNEWHILL PLACEEAST THIRD STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonSILVER STE STDORCHESTER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonSLEEPER STCONGRESS STSEAPORT BLVDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonSUMMER STEAST FIRST STELKINS STFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
South BostonSUMMER STEAST FIRST ST ELKINS STFull ReconstructionAPRIL- JULY4 MONTHSACTIVE  
South BostonTHOMAS PARKG STG STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonTHOMAS PARKG STG STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonTUDOR STLILLY STDORCHESTER STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South BostonWOODWARD STDORCHESTER AVDORCHESTER STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndEAST BERKELEY STWASHINGTON STALBANY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndEAST CANTON STALBANY STHARRISON AVPrivate Development ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/5/20
South EndEAST CONCORD STWASHINGTON STFATHER FRANCIS J GILDAY STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndEAST DEDHAM STALBANY STHARRISON AVPrivate Development ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/5/20
South EndPAUL PLSHAWMUT AVHERALD STFull ReconstructionFEBRUARY6 MONTHSACTIVE 
South EndRUTLAND STSHAWMUT AVTREMONT STCapital ResurfacingJULY2 WEEKSCOMPLETED7/17/20
South EndTRAVELER STWASHINGTON STHARRISON AVSignal Installation WorkSEPTEMBER 20191 YEARACTIVE 
South EndWALTHAM STUNION PARK STTREMONT STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndWASHINGTON ST HERALD STEAST BERKELEY STAsphalt ResurfacingSEPTEMBER 20191 YEARACTIVE 
South EndWASHINGTON STEAST BERKELEY STHERALD STFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
South EndWEST CANTON STTREMONT STCOLUMBUS AVCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
South EndWEST SPRINGFIELD STTREMONT STCOLUMBUS AVAsphalt Resurfacing20202 WEEKSMAJOR UTILITY WORK IN 2019 WILL DELAY PAVING UNTIL 2020 
West RoxburyBAKER STCENTRE STJOHNSON STAsphalt ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
West RoxburyBAKER STJOHNSON STSPRING STAsphalt ResurfacingSEPTEMBER2 WEEKSNOT STARTED 
West RoxburyCENTRE SST WR JP RXW ROXBURY PKWYMT VERNON ST JPAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburyCHAPIN AVPRESTON STMT VERNON STFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
West RoxburyEMMONSDALE STLINNET STHOWITT RDCapital ResurfacingJULY2 WEEKSCOMPLETED7/31/2020
West RoxburyFARMINGTON RDVFW PARKWAYWILLOW ST WRCapital ResurfacingJULY2 WEEKSNOT STARTED 
West RoxburyGARNET RDWELD STFARMINGTON RDCapital ResurfacingJULY/AUGUST2 WEEKSCOMPLETED8/1/2020
West RoxburyIVORY STDENT STTEMPLE ST WRCapital ResurfacingAUGUST/SEPTEMBER2 WEEKSCOMPLETED8/31/2020
West RoxburyJACQUELINE RDBIRCHLAND AVANSONIA RDFull ReconstructionTO BE DETERMINED2 MONTHSNOT STARTED 
West RoxburyLAGRANGE STAT BELLEVUE HILL RDAT BELLEVUE HILL RDSidewalk ReconstructionTO BE DETERMINED3 MONTHSNOT STARTED  
West RoxburyLANDSEER TERRACELANDSEER STDEAD ENDAsphalt ResurfacingAUGUST2 WEEKSCOMPLETED8/7/2020
West RoxburyMARCH AVPARK STBELLEVUE STAsphalt ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/4/2020
West RoxburyMONCLAIR AVSUNSET HILL RDCOLBY STCapital ResurfacingJULY2 WEEKSNOT STARTED 
West RoxburyPARK STWOODARD RDROBIN STAsphalt ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/4/2020
West RoxburyPOMONA AVSANBORN AVCHESBROUGH RDCapital ResurfacingAUGUST/SEPTEMBER2 WEEKSCOMPLETED8/31/2020
West RoxburyRUSSETT RDESTHER RDWELD STAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburySELWYN STCONISTON RDARDALE STCapital ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburySPRING STCENTRE ST WR JP RXDEDHAM TOWN LINEAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburySTEARNS RDWASHINGTON STDEAD ENDAsphalt ResurfacingTO BE DETERMINED2 WEEKSNOT STARTED 
West RoxburySUNNYBANK RDMAPLE STDEAD ENDAsphalt ResurfacingAUGUST2 WEEKSCOMPLETED8/7/2020
West RoxburySWAN STLA GRANGE ST WRPHEASANT STCapital ResurfacingAUGUST/SEPTEMBER2 WEEKSCOMPLETED8/31/2020
West RoxburyTOBIN RDWASHINGTON STPLEASANTDALE RDAsphalt ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/4/2020
West RoxburyWESTMOUNT AVMT VERNON STLAGRANGE STAsphalt ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/11/2020
West RoxburyWESTOVER STWELD STFARMINGTONCapital ResurfacingSEPTEMBER2 WEEKSCOMPLETED9/10/2020
         
 
Text Size: XX-Small Font Size X-Small Font Size Small Font Size

     
Privacy & Security Divider © City of Boston