Pedestrian access ramp replacement takes place in seven stages
Four inches of existing ramp is excavated
Excavated area is compacted and leveled
Edge stone is reset
6' landing is formed using boards
Concrete is poured for the landing and/or bricks are laid for the landing. Concrete is brushed 30 minutes after pour to produce a non-stick surface
Ramp is formed using boards
Concrete is poured for the ramp and/or bricks are laid for the ramp. Concrete is brushed 30 minutes after pour to produce a non-stick surface.